Current Projects
- Upgrade Server Network - Q2-2012
- Deploy Dell M6348 Stacked Switches for Servers
- Provide Guest Wireless Internet Access - Q2-2012
- Technical solution deployed. Documentation being finalised.
- Handover User Access connections in Jacqui Wood Centre (formerly TMRC) from CLS to ICS - Q2-2012
- Remaining connection repatching being coordinated with CMDN CAMS
- Upgrade Access switches to use 10Gb Uplinks - Q2-2012
- Required parts being priced with supplier
- Dynamic VLAN assignment to access ports - Q2-2012
- Technical solution being designed
- Evaluating Opensource PacketFence NAC product.
- Deploy Network Admission Control - Q2-2012
- Evaluating options in conjunction with Dynamic VLAN assignment
- Deploy Private VLANs with ACLs for all instrument/acquisition machines - Q2-2012
- Test IPv6 connectivity between CLS and UoD - Dependent upon ICS
- CLS test deployment live on capable equipment
- Provide further switchports in MSI Building to accommodate CAHID extension - Q2-2012
- Equipment acquired and work to be scheduled for a suitable time
- Deploy SSL VPN - Q2-2012
- Software being packaged for supported computer platforms
- Transition from RFC1918 and NAT to real IPv4 addresses - Dependent upon ICS
- ICS working to provide CLS with the necessary IPv4 netblock
Completed Projects
- Fibre installed between PG2 and JBCG Data Centres to support Server Network upgrade
- Investigate 10GbE Switching solutions
- Investigate and cost IPv6 deployment
- Deploy simultaneous IP and ISDN Video Conferencing Service
- Service Network Switch UPSs